I belief this would be a critical scenario so needs to understand the options.
I belief this would be a critical scenario so needs to understand the options.
If concrete starts setting before placement, it is a serious quality issue. Your response must prioritize structural integrity over speed.
Immediate Actions on Site 1. Stop the Pour ImmediatelyDo not place partially set concrete
Prevent compromised concrete from entering the structure
Check:
Loss of workability
Stiffness / false set vs initial set
Perform slump test if possible
Re-tempering is not allowed
Adding water reduces strength and durability
If concrete has started initial setting:
Reject the batch
Return to plant or dispose as per procedure
Report:
Delay in transport
Traffic or breakdown
High ambient temperature
Document the rejection
(Only with written approval)
Use approved retarding admixture
Only if:
Concrete is still within allowable setting time
Engineer-in-charge approves
Plan pour during cooler hours
Minimize transit time
Use retarders in hot weather
Ensure continuous supply and manpower readiness
If concrete has started setting before pouring, I stop the work, do not add water, assess the condition, reject the concrete if initial setting has begun, and inform the senior engineer and batching plant.